BINTAN 200MWAI Data Center
03 / Infrastructure Campus · Power · Water

Everything inside the fence.

The campus masterplan, the 640MW captive plant, and the 30 million cubic metre reservoir. All three are already built or under construction, so there is no queue and no dependency on external approvals.

Campus masterplan

Nine parts, one fence line

Four 50MW halls, central diesel spine, captive plant, tank row and 220kV substation — short runs, symmetrical distribution.

Light DayOne-style campus rendering with four halls and foreground reservoir
PLATE · CAMPUS · Phase 1 halls and water edge — DayOne light render
On the plot

Short cable trenches. Same path to every hall.

Daylight view of the Phase 1 plot. The four 50MW halls sit either side of the central diesel spine. The 640MW captive plant is to the north-west, already built and owned. The reservoir lies 20 m south of the boundary and feeds the tank row.

Every hall sees the same distance to generation, the same water head, the same fibre path to Singapore.

4 × 50 MW halls 22 m hall height 30–40 ha Phase 1
Energy path

Plant → SS → spine → halls

Orange path lights in sequence when the figure enters view.

FIG. POWER · Plant → SS → spine → H1–H4 · flow runs the full feeder into each hall

Masterplan

Physical specification

Phase 1 envelope, Galang Batang SEZ
ElementQuantityDimension or ratingNote
Data halls450 MW IT each, 3 floorsTotal Phase 1 IT load 200 MW
Hall height22 mClear height 12 mHeadroom for GB300 pipework and roof plant
Floor loading≥ 20 kN/m²Raised floor in hall, slab in plant rooms
Generator buildings280 × 2,500 kWN+1, centre line between halls
Fuel store148 h at full loadBelow grade, pumped to day tanks
Substation1220 kV, dual routeFeeds 800 V DC distribution
Water tanks81,250 m³ each10,000 m³ on site
Site area, Phase 130 to 40 haServiced, title clearLand banked to 3 GW
Why it is laid out this way

Three decisions that cost money once and save it later

Decision 01

Halls on the outside, generation in the middle

Every hall sits on the perimeter with a short, straight run back to the generator spine. No hall depends on a neighbour for a cable route, so a fault in one hall stays in that hall.

Decision 02

22 m halls, not 12 m

Building taller once is cheap. Retrofitting a taller hall later, once a liquid cooling loop and overhead busway are already installed, is not. The headroom is there from day one for whatever comes after GB300.

Decision 03

Water on the north edge, reservoir to the south

The tank row is a 20 m pipe run from the reservoir through treatment, not 400 m. Gravity helps. The 48 h fuel store is below grade so it does not compete for floor plate.

South entrance and operations office
PLATE 04 · Main entrance, security and visitor staging
Arrival

Gate on the west. NOC sees every truck.

The main gate faces the access road from Galang town. Security checkpoint, vehicle wash, and a covered staging bay for inbound server crates. The operations office looks onto the yard.

Visitor access is controlled to the office and the viewing gallery. The data halls are behind two doors and a biometric reader.

Power

640MW on site. Phase 1 uses 39% of it.

640MW Installed generation

Owned, not contracted. No queue position to hold.

$0.088/kWh Delivered cost

Roughly a third of Singapore commercial power.

1.8% Transmission loss

Plant to rack. AC distribution lands around 5%.

99.99% Monthly availability

Written into the lease, with rent credit if we miss it.

Distribution

800 V DC busway at 1,500 A feeds each hall. Silicon carbide solid-state transformers convert from the 220 kV substation. Transmission loss from plant to rack is 1.8%, compared to roughly 5% for AC.

Redundancy

N+1 diesel fleet with 48 hours of fuel at full load stored below grade. 20 MW / 40 MWh battery store absorbs load steps and provides instant ride-through.

Energy flow

From turbine terminal to rack

Generation — 80 × 2,500 kW generators, N+1. Each unit can hot-swap without dropping the load.

Switchyard — 220 kV collection, dual route. One route down, one route up, no single point of failure.

Conversion — Solid-state 220 kV to 800 V DC, silicon carbide devices, 98.2% efficiency.

Distribution — 800 V DC busway, 1,500 A per hall, overhead so every tap is visible and maintainable.

Rack entry — PDU shelves drop 800 V to 48 V DC at the rack, N+1 per shelf.

Fuel — Below-grade store holds 48 hours at full load. Day tanks auto-refill from the main store.

Battery buffer — 20 MW / 40 MWh LiFePO4 absorbs load steps, covers generator start-up, provides ride-through.

Testing — Weekly load-bank test, monthly full-load run, quarterly maintenance swap.

Monitoring — DCDC exposes bus voltage, current, and temperature to your DCIM via a read-only API.

Water

30 million cubic metres, 20 metres away.

30M m³ Reservoir capacity

Owned. Sitting at the south boundary, 20 m from the fence.

10M m³ On-site tankage

Eight tanks at 1,250 m³, fed from the reservoir.

10yrs+ Make-up reserve

Annual make-up is 6% to 7% of reservoir capacity.

0L Municipal draw

Zero competition with local residential supply.

Closed loop

The cooling circuit is closed. The only water that leaves the site is water we treat and put back. No withdrawal permits, no competition with agriculture or residential supply.

Future proof

Beyond 1 GW we switch to seawater source heat rejection using the island's coastal position. That drops fresh water use toward zero.

Waterfront view of the campus reservoir edge
PLATE · Reservoir edge · whole cooling budget in one place
The reservoir

The whole cooling budget, in one place

Size — 30 million cubic metres, 20 m deep. Enough for 10 years of make-up at current draw.

Treatment — Sand filters, UV, and chemical dosing. No biofilm, no scaling.

On-site tankage — Eight 1,250 m³ tanks buffer the supply. Dedicated fire pump house draws from the same reservoir.

Water detail